O-16

?ADVERTISEMENT FOR BIDS
This project is issued for Bids by:
Cameron Parish Police Jury
c/o Porche|May+Domain Architecture
1808 Elm Street,
Lake Charles, LA 70601
Submit sealed bids to Owner, c/o the Architect above before 2:00 p.m. on Thursday, November 11, 2021.
for: Post Hurricane Restoration Project to rebuild at 3 locations
East Annex
110 Smith Circle, Cameron, LA 70631 – CPPJ Location LOC 50
West Annex
148 Smith Circle, Cameron, LA 70631 – CPPJ Location LOC 35
Cameron Parish Courthouse
119 Smith Circle, Cameron, LA 70631 – CPPJ Location LOC 2
Complete Bid Documents prepared by Porche|May+Domain Architecture, 1808 Elm Street, Lake Charles, LA 70601 for this project are available in electronic form. The Bid Documents may be obtained free of charge by contacting:
Letterman’s Printing & Graphics: lettermansbidconnect.com
Printed copies are not available from the Architect. Printed copies can be ordered from Letterman’s at Contractor’s expense.
A MANDATORY PRE-BID
CONFERENCE WILL BE HELD
10:00 a.m. on Tuesday, November 2, 2021; beginning at the front of the East Annex, 110 Smith Circle, Cameron, LA 70631; and then to the other sites thereafter.
Bidders shall visit project sites to become familiarized with the site and working conditions.
Bids shall be accepted from Contractors who are licensed under LA. R.S. 37:2150-2192 for the classification of Building Construction.
No bid may be withdrawn for a period of 30 days after receipt of bids, except under the provisions of LA. R.S. 38:2214.
The Owner reserves the right to reject any and all bids for just cause. In accordance with La. R.S. 38:2212(B)(1), the provisions and requirements of this Section and those stated in the bidding documents shall not be waived by any entity.
The successful Bidder shall be required to furnish a Performance and Payment Bond as described in the Instructions to Bidders.
This project may be financed or eligible for reimbursement in whole or in part by federal or other funds. The Owner shall incur no obligation to the Contractor until the Contract Between Owner and Contractor is fully executed.
Contract Time & LD’s
Construction/Contract Time: 210 calendar days
Liquidated Damages: $500.00 per calendar day
RUN: Oct. 14, 21, 28 (O 16)